subscribesubscriber servicescontact usabout ussite map
 
December 2, 2005

Plant repairs at issue

County officials, design/builder debate warranty

      TRAVERSE CITY - Grand Traverse County officials and the design/builder of its septage treatment facility are at odds again over a contract amendment to cover repairs to the failed facility.
      The design/builder, Gourdie-Fraser/Christman LLC, offered a three-year warranty on repairs while the county wants a five-year renewable warranty secured by a bond.
      "We need a long warranty, especially after what we've been through," said East Bay Township supervisor Glen Lile, a member of a county committee that oversees the facility.
      The plant has three sets of tanks. Membrane tanks where a wall collapsed in June will be completely rebuilt under the supervision of NTH Consultants, an independent engineering firm.
      The other two sets of tanks need structural steel added to concrete walls, reinforcement that had been omitted by a subcontractor. The tanks also hadn't been designed to the industry standard of ACI 350 to reduce cracking and leaks.
      Gourdie-Fraser/Christman proposed to cut the concrete walls vertically, creating more expansion joints to obtain the same result as ACI 350.
      County attorney Michael Houlihan said NTH and Gourdie-Fraser/Christman can't show where similar fixes have been attempted.
      "It's uncharted ground, and somebody needs to stand behind it," Lile said.
      Gourdie-Fraser/Christman has not responded to repeated calls for comment.
      Under Houlihan's proposed warranty, the tanks will be leak-tested and inspected in five years. If they don't pass inspection, the design/builder will make repairs, the warranty is extended for another five years and the whole process starts over and continues until the tanks perform as they should.
      The expected life of the tanks is 50 years.
      County officials, however, say they are willing to discuss some changes to the warranty.
      "We want and expect five years with a renewal, but would that be indefinite for 30 or 40 years? I don't know if that's feasible," county administrator Dennis Aloia said.
      Gourdie-Fraser/Christman requested clarification of some other issues but so far is no longer balking at promising - in writing - to cover all costs of repairs along with the county's administrative, engineering and legal costs.
      The firm has paid the county's first bill for lost revenue and legal costs, Houlihan said.

See Related Stories:
      Plant designer says it didn't know about standard - November 10, 2005
      Septage repairs outlined - November 10, 2005
      Consultants to offer final septage report - November 9, 2005
      Subcontractor questions collapse fault - November 4, 2005
      Septage report cites company's omission - October 19, 2005
      Acme wants Houlihan removed from investigation - October 15, 2005
      Septage plant collapse explanation coming - October 15, 2005
      County officials back Houlihan in septage investigation - October 7, 2005
      Septage 'debacle' questioned; Supervisor wants all info - October 4, 2005
      Public awaits report on collapse of septage plant - September 27, 2005
      Taxpayers won't foot bill for septage plant repairs - July 26, 2005
      Officials looked for 'spin' in septage plant collapse - July 23, 2005
      Septage spill situation becoming muddled, attorney says - July 23, 2005
      Septage plant repairs tagged at $2 million - July 19, 2005
      Health risk from septage plant failure said minimal - July 19, 2005
      Well owners near septage plant fear contamination - June 25, 2005
      GT County's septage treatment plant may reopen - June 22, 2005
      Septage plant 'structural failure' is investigated - June 21, 2005
      Burst tank rocks GT County's new septage plant - June 19, 2005

See Related Editorials:
      Plant collapse exposed failed system - November 15, 2005
      Aloia deserves credit for putting public first - October 2, 2005
      Septage plant solution must be public process - September 18, 2005
      Finally, facts to ordain who pays for new septage plant - September 13, 2005
      Septage plant contract puts the taxpayers last - September 6, 2005
      Plant collapse inquiry is stuck in 'spin' cycle - August 3, 2005

Premier Guide
Find a business

Walking Fingers
Maps, Menus, Store hours, Coupons, and more...
Premier Guide
Find a new or used car
Find a new home
Find a new job

Top Autos & More

Top Stuff

Top Real Estate

Top Rentals